Radiogram No. 2800 u                                                                                                                          for 01.25.02

 

EVA-6              January 25, 2002

ISS-4:   EV1 – Yuri Onufrienko                   EV2 – Dan Bursch            IV – Carl Walz

 

EXTRAVEHICULAR ACTIVITY TIMELINE

 

Installation of СКК№1-DC, installation of PLATAN-M payload, installation of СКК№2-SM, installation of ГЗУ plume deflectors, retrieval of KROMKA1-0 payload, installation of KROMKA1 payload, installation of СКК№1-SM, installation of WA4 Ham Radio Antenna

 

No.

Operator

Task Description

Duration (minutes)

GMT

DMT

Orbital Night

15:09 – 15:43 (18:09 – 18:43)

1

EV1

Open EV hatch 1 (ОВЛ1)

:06

15:35 -15:41

18:35 -18:41

2

EV1

Install protective ring (ЗК)

:03

15:44

18:44

3

EV1

Egress DC

:04

15:48

18:48

4

EV1; EV2

Transfer EVA cluster №1 (Plume Deflectors (ГЗУ) + Ham Radio Antenna WA4) onto EV Ladder (ВУ)

:03

15:51

18:51

5

EV1; EV2

Transfer EVA cluster №2 (EVA Tool Carrier (КПУ) + small frame + KROMKA 1 payload + Semi-rigid airtight container (ПГК) + СКК№1-SM + СКК№2-SM + PLATAN-M payload + СКК№1-DC) onto EV Ladder (ВУ)

:03

15:54

18:54

6

EV2

Egress DC

:02

15:56

18:56

7

EV1

Separate СКК№1-DC from EVA cluster №2 and transfer it along HRs 3030 and 3031 to HR3032

:02

15:58

18:58

8

EV1

Install СКК№1-DC on HR3032 (secure lock with wire tie), remove protective cover, deploy and take photos

:05

16:03

19:03

9

EV1

Translate onto EV Ladder (ВУ) along HR3031 & 3030, secure protective cover of СКК№1-DC near EV Hatch 1 (ВЛ1)

:01

16:04

19:04

10

EV2; EV1

Combine EVA clusters №1 & №2 into single cluster

:01

16:05

19:05

11

EV1; EV2

Transfer combined EVA cluster along EV Ladder gap spanner (ФПД ВУ), HRs 2313, 2314, 2315, 2316, 2317, 2318, 2411 to HR2411

:06

16:11

19:11

12

EV1; EV2

Separate PLATAN-M from combined EVA cluster and transfer it along HRs 2443, 2442, 2441, 2434, 2435, 2433 to HR2433

:06

16:17

19:17

13

EV1; EV2

Install PLATAN-M (secure lock with wire tie) on HR2433, deploy and take photos

:05

16:22

19:22

14

EV1; EV2

Translate to combined EVA cluster along HRs 2433, 2435, 2434, 2441, 2442, 2443 to HR2411 (if necessary, wait for attitude thruster inhibit and, if time allows, visually inspect and take photos of Window 7 area)

:05

16:27

19:27

15

EV1; EV2

Translate combined EVA cluster along HRs 2411, gap spanner (ФПД) on SM РО2 cone, HRs 2511, 2541

:02

16:29

19:29

16

EV2

Separate Fairlead-1 from combined EVA cluster and install it on HR 2541 (next to standoff closest to ПхО)

:02

16:31

19:31

17

EV2; EV1

Translate combined EVA cluster along HRs 2512, 2542, 2611, 2647 to HRs 2611 & 2647 on SM Assembly Compartment (АО)

:02

16:33

19:33

18

EV1; EV2

Separate СКК№2-SM from combined EVA cluster, transfer it along HRs 2646, 2645, 2644, 2746. 2745, install (secure lock with wire tie) on HR2745, remove protective cover, deploy and take photos if possible, return to combined EVA cluster and attach protective cover to КПУ

:07

16:40

19:40

19

EV2

Separate Fairlead-2 from combined EVA cluster and install it on HR 2646 (next to standoff between HR2646 and HR2647)

:02

16:42

19:42

Orbital Night (crew rest)

16:42 – 17:15 (19:42 – 20:15)

20

EV1; EV2

Split combined EVA cluster, secure EVA cluster №2 on HR2647 by the КПУ lock, secure EVA cluster №1 on HR2646 and HR2612

:04

17:19

20:19

21

EV1; EV2

Separate ГЗУ ”РIV” from EVA cluster №1, install and take photos

:09

17:28

20:28

22

EV1; EV2

Separate bundle ГЗУ ”КI”,”ТI” + Antenna WA4 from EVA cluster, transfer it along HRs 2645, 2644, 2643, 2642, 2641, and secure on HR2641

:06

17:34

20:34

23

EV1; EV2

Install Antenna WA4 with 6 cable clamps on HR2642 (secure antenna lock with wire tie)

:04

17:38

20:38

24

EV1; EV2

Translate along HRs 2643, 2644, 2645, 2648, separate from clusters and transfer bundle ГЗУ ”РII” + ПГК along HRs 2648, 2613, 2614, 2615, 2616, 2619, 2623, 2618, 2622, 2624 (wipe HRs 2614 & 2615 with towel)

:11

17:49

20:49

25

EV2; EV1

Remove KROMKA1-0 from HR2624 and place it into ПГК, secure ПГК with KROMKA1-0 on HR2622

:06

17:55

20:55

26

EV1; EV2

Install ГЗУ ”РII” and take photos (if possible)

:09

18:04

21:04

27

EV2; EV1

Transfer ПГК with KROMKA1-0 along HRs 2622, 2618, 2623, 2619, 2616, 2615, 2614, 2613, 2648, and attach it to КПУ

:08

18:12

21:12

28

EV2; EV1

Separate ГЗУ ”ТI” from ГЗУ ”КI”

:02

18:14

21:14

Orbital Night (crew rest)

18:14 – 18:48 (21:14 – 21:48)

29

EV1; EV2

Transfer ГЗУ ”КI” and ”ТI” along HRs 2613, 2614, take photos of installation area

:04

18:52

21:52

30

EV1; EV2

Install ГЗУ ”ТI”

:06

18:58

21:58

31

EV1; EV2

Install ГЗУ ”КI”, wipe ORLAN gloves with towel

:09

19:07

22:07

32

EV1; EV2

Separate KROMKA1 from EVA cluster №2, remove protective cover, install, and secure it on collapsible HR of ГЗУ ”ТI”, take photos of KROMKA1 and ГЗУ ”КI” & ”ТI”

:06

19:13

22:13

33

EV1; EV2

Translate to bundle ГЗУ ”КIII” + ”ТIII” along HRs 2613, 2648, 2645, 2644, 2643, 2642, 2641

:07

19:20

22:20

34

EV1; EV2

Separate ГЗУ ”ТIII” from ГЗУ ”КIII”, transfer it along HRs 2634, 2633 (wipe HRs 2633, 2635 and 2632 with towel), take photos of installation area of ГЗУ ”КIII” & ”ТIII”

:05

19:25

22:25

35

EV1; EV2

Install ГЗУ ”ТIII”

:06

19:31

22:31

36

EV1; EV2

Install ГЗУ ”КIII”, wipe ORLAN gloves with towel, take photos of ГЗУ ”КIII” and ”ТIII”

:09

19:40

22:40

37

EV1; EV2

Install cable clamps in openings labeled ”11”, ”12”, ”13”, and ”14”, and on HR2641 (install cable clamp 6 (backup) in opening labeled ”16”)

:10

19:50

22:50

Orbital Night (crew rest)

19:47 – 20:20 (22:46 – 23:20)

38

EV1; EV2

Route and place Antenna WA4 cable into the cable clamps, mate connectors ХФП11-4, secure cable slack, check installation of Antenna WA3, use additional wire tie to secure antenna if necessary

:09

20:29

23:29

39

EV1; EV2

Take photos of the open ФП11 connector plate, slacked cable, cable clamps with routed cable, closed ФП11 connector plate, Ham Radio Antennas WA3 & WA4

:06

20:35

23:35

40

EV1; EV2

Translate along HRs 2633, 2634, 2641, 2643, 2644, 2645, 2648, 2646 to EVA cluster №2

:05

20:40

23:40

41

EV1

Separate СКК№1-SM from EVA cluster №2, install it on HR2611 (secure lock with wire tie), remove protective cover and deploy, take photos, attach protective cover on КПУ

:06

20:46

23:46

42

EV1; EV2

Translate with bundle (КПУ + small frame + ПГК with KROMKA1-0) along HRs 2646, 2612, 2611, 2647, 2542, 2512, 2541, 2511, gap spanner (ФПД) on SM РО2 cone, and HR2411 to HR2411

:07

20:53

23:53

43

EV1; EV2

Visually inspect and, if possible, take photos of Window 7 area

:06

20:59

23:59

44

EV1; EV2

Translate to DC EV hatch 1 with bundle (КПУ + small frame + ПГК with KROMKA1-0) along HRs 2318, 2317, 2316, 2315, 2314, 2313 and DC EV Ladder

:04

20:03

23:03

45

EV2

Ingress DC

:02

20:05

23:05

46

EV2

Transfer bundle (КПУ + small frame + ПГК with KROMKA1-0) and protective cover of СКК№1-DC into DC-1

:02

21:07

00:07

47

EV2

Ingress DC

:03

21:10

00:10

46

EV2

Remove protective ring (ЗК)

:03

21:13

00:13

47

EV2

Close EV hatch 1 (ЗВЛ)

:06

21:19

00:19

Orbital Night

21:19 – 21:52 (00:19 – 00:52)

 

 

 

Total EVA duration: 5 hours 44 minutes

 

 

 

End of radiogram