[eagle] TeamSpeak conference for Tuesday 16 Jan
Jim Sanford
wb4gcs at amsat.org
Mon Jan 8 19:26:27 PST 2007
Team:
I'm sending this out by email because I'm having some difficulties with
the TS page on EaglePedia.
Things I'd like to discuss:
70cm RX status
How many prototypes to build
Goals for 2007
My partial goals are:
Prototype 70cm RX and 2m TX
Demonstrate above, with some form of SDX prototype
Demonstrate prototype IHU-3 and CAN widgets
Structure design and model
Refine microwave phased array plans
Peer review, test, demonstrate text messaging
Begin development of integration plan and composite test plan
Develop Work Breakdown Structure (WBS) leading to a preliminary
development/construction schedule
The last item is clearly mine; Gould has been helping me on the WBS.
Obviously, once I've laid it out, I'll need your comments and then some
schedule estimates. I think that we are now at the point where it's
time to define a schedule of what is reasonably achievable so that we
can begin to make construction/integration/launch plans.
Please add to the goals; this is just my first cut.
Please also add to topics.
I've asked for help on my issue with EP; will advise as soon as the
agenda is posted there.
Thanks & 73,
Jim
wb4gcs at amsat.org